Tom
Member
- Messages
- 1,136
- Location
- Charente, France
Last night it dropped down to 3.9 degrees here (Lincolnshire). I'm almost done with the work outside (for this year, anyway!) and only have 4 quoins to fit, which are currently on order from the quarry. I'm hoping to have these within a couple of weeks. The mortar will be 3:1 Sand:Hydraulic Lime. Will it be ok to do this last bit of work? If I do it, should I try to cover the area with hessian (although that would be quite tricky) or would it make no difference? I'd be happy to leave this work until next year if it were possible but the area is load bearing (1/4 up on the corner of the the house) and the stone there at present is very weak. Any help would be gratefully received. Thanks.
Jaqy
Jaqy