I was hoping for some advice here. I have been resotring a grade 2 listed georgian semi for the last 18 months. I am having an extension build and all my windows are bespoke.
The long and short of it is: I was ordering the windows and doors in two orders. I first asked them to sart the 1st half in early March. I had 4 windows delivered last wednesday and 3 of them didnt fit, and had to have either side panels taken off them and or planed to go in the holes. I was also expecting at the very least a big door with a fan light. I also thought i had a set of double doors and another single door being delivered, but there would appear they had a 'miscommunication'.
The thing is, i am paying £15k for the windows and doors and after 4 months they have supplied 4 windows, of which 3 had to be made to fit.
on monday I said i want to cancel the rest of the order as i have no faith in their urgency or confidence that they are going to fit. I was elequently told this morning that if i do that i will have to pay for the work and time on the other windows they started which they measured up for last thursday lunch time. I said they should balance that figure against the delay and windows that dont fit.
I feel like i am being bullied into them finishing off all my windows and doors because i cant afford the fight or time delay getting someone else in ( i have spoken to another firm who said 8 weeks from monday and have my drawings).
What should i do? any advice?
The long and short of it is: I was ordering the windows and doors in two orders. I first asked them to sart the 1st half in early March. I had 4 windows delivered last wednesday and 3 of them didnt fit, and had to have either side panels taken off them and or planed to go in the holes. I was also expecting at the very least a big door with a fan light. I also thought i had a set of double doors and another single door being delivered, but there would appear they had a 'miscommunication'.
The thing is, i am paying £15k for the windows and doors and after 4 months they have supplied 4 windows, of which 3 had to be made to fit.
on monday I said i want to cancel the rest of the order as i have no faith in their urgency or confidence that they are going to fit. I was elequently told this morning that if i do that i will have to pay for the work and time on the other windows they started which they measured up for last thursday lunch time. I said they should balance that figure against the delay and windows that dont fit.
I feel like i am being bullied into them finishing off all my windows and doors because i cant afford the fight or time delay getting someone else in ( i have spoken to another firm who said 8 weeks from monday and have my drawings).
What should i do? any advice?