I've got the following tasks to do and I've no idea in which order to do them. The end of the house is gutted i.e no floorboards upstairs, just roof beams and joists and raked-out stone walls ready for pointing, no wiring and no plumbing.
I've got to:
Repoint the walls
Lay new floorboards
Build partition stud walling upstairs and downstairs
Fix plasterboard onto roof rafters
I've talked to the electrician and plumber and know what they need before they can return, but do I fix the plasterboard onto the rafters before repointing or afterwards? And do I build the stud walling on top of the new floor or do I wait and fix the floor around the stud walling? My natural inclination is to:
Repoint
Put new floors down
Build stud walling
Fix plasterboard
Does it make any difference?
I've got to:
Repoint the walls
Lay new floorboards
Build partition stud walling upstairs and downstairs
Fix plasterboard onto roof rafters
I've talked to the electrician and plumber and know what they need before they can return, but do I fix the plasterboard onto the rafters before repointing or afterwards? And do I build the stud walling on top of the new floor or do I wait and fix the floor around the stud walling? My natural inclination is to:
Repoint
Put new floors down
Build stud walling
Fix plasterboard
Does it make any difference?