TheRoost
Member
- Messages
- 208
- Location
- Trafford, South Manchester
We're going to be doing some patch pointing soon, using NHL 3.5, the worst bits are the horizontal joints just above ground level, where the old mortar has eroded to a full brick depth in places (i.e. 4.5" )
Some of the online guides for repointing say that deep joints should be built up in layers, with four days between coats! what I can't find anywhere is how deep each layer should be as a maximum, one suggests 10mm layers but that would take forever!
For normal area's of repointing where raking out is needed, would you apply the mortar in one layer, e.g. 25mm deep? so would it be reasonable to build up deep joints in 25mm layers, or could you go more?
Thanks.
Andy
Some of the online guides for repointing say that deep joints should be built up in layers, with four days between coats! what I can't find anywhere is how deep each layer should be as a maximum, one suggests 10mm layers but that would take forever!
For normal area's of repointing where raking out is needed, would you apply the mortar in one layer, e.g. 25mm deep? so would it be reasonable to build up deep joints in 25mm layers, or could you go more?
Thanks.
Andy