Hi, I saw a similar thread but for clarity thought it best to open a new discussion.
We are renovating our kitchen in our 1890 ground floor flat. It is 3 course brick and cement construction and the kitchen is in an outrigger with a recently laid concrete floor. The walls are 3 courses brick construction. We've hacked off the patchwork of concrete/plaster/plasterboard and taken it back to brick throughout.
I intend to batten and board the walls then have them skimmed. Originally we were thinking 2 x 1 battens with a 12.5mm plasterboard and 25mm polystyrene between the battens as this would give us a bit better insulation without widening the walls too much. However we were then advised that we'd be better to keep an air gap between the battens and line with thermal board (e.g. gyproc thermaline). Does this sound right? And if so, how important is it to have a vapour control layer on the back of the thermal board? Clearly this method is more expensive and reduces the room size a little bit more too so I want to ensure this is the right thing to do.
In case it matters - the walls are nicely dry although there is a little rising damp in the bottom of two external corners but it is not rising above the injected DPC. Its hard to know the cause of this damp - it could be from the poor/old plumbing - a leadlock was leaking a little and a cast iron waste pipe had rotted through near to these corners. These will all be replaced. It could also be coming through the walls below ground level because the troughs around the outside of the walls had become filled with organic matter which we have now dug out. Or it could be something else - maybe caused by the recent concrete floor and DPC forcing the water out and to the sides.
Anyway, any suggestions about how we should dry line would be most appreciated. And where we can find the materials at competitive prices would also be very helpful!
Many thanks
Chris
We are renovating our kitchen in our 1890 ground floor flat. It is 3 course brick and cement construction and the kitchen is in an outrigger with a recently laid concrete floor. The walls are 3 courses brick construction. We've hacked off the patchwork of concrete/plaster/plasterboard and taken it back to brick throughout.
I intend to batten and board the walls then have them skimmed. Originally we were thinking 2 x 1 battens with a 12.5mm plasterboard and 25mm polystyrene between the battens as this would give us a bit better insulation without widening the walls too much. However we were then advised that we'd be better to keep an air gap between the battens and line with thermal board (e.g. gyproc thermaline). Does this sound right? And if so, how important is it to have a vapour control layer on the back of the thermal board? Clearly this method is more expensive and reduces the room size a little bit more too so I want to ensure this is the right thing to do.
In case it matters - the walls are nicely dry although there is a little rising damp in the bottom of two external corners but it is not rising above the injected DPC. Its hard to know the cause of this damp - it could be from the poor/old plumbing - a leadlock was leaking a little and a cast iron waste pipe had rotted through near to these corners. These will all be replaced. It could also be coming through the walls below ground level because the troughs around the outside of the walls had become filled with organic matter which we have now dug out. Or it could be something else - maybe caused by the recent concrete floor and DPC forcing the water out and to the sides.
Anyway, any suggestions about how we should dry line would be most appreciated. And where we can find the materials at competitive prices would also be very helpful!
Many thanks
Chris